Projects
| SN | Project Name | Client | Contract Value (₹) | Location | Type |
|---|---|---|---|---|---|
| 1 | Earth Work in Ganga Expressway Pkg-11 | ITD | 9,00,00,000.00 | Raebareli | Roads |
| 2 | Earth Work in Ganga Expressway Pkg-12 | ITD | 23,34,00,000.00 | Kunda (UP) | Roads |
| 3 | Earth work on Jodhpur Ring Road Bypass | MCC | 3,10,00,000.00 | Jodhpur (Raj) | Roads |
| 4 | Ghazipur - Ballia 4 Lane | Ravi Infrabuild Pvt. Ltd | 9,00,00,000.00 | Ghazipur (UP) | Roads |
| Total Value Of Ongoing Work | 44,44,00,000.00 | ||||
| SN | Project Name | Client | Contract Value (₹) | Location | Type |
|---|---|---|---|---|---|
| 1 | Unnao-Lucknow Expressway | LNT | 13,21,00,000.00 | Unnao (UP) | Roads |
| 2 | Deogarh–Sanchore Expressway Pkg-4 (Amritsar–Jamnagar) | Lakshmi Infra & Developers | 4,23,00,000.00 | Jalore (Raj) | Roads |
| 3 | Mumbai–Nagpur Expressway Pkg-2 (Village Khadki to Amagaon) | AFCONS | 14,56,00,000.00 | Wardha (MH) | Roads |
| 4 | Agra–Lucknow Expressway (3.5KM) | AFCONS | 13,25,00,000.00 | Uttar Pradesh | Roads |
| 5 | Bundelkhand Expressway Pkg-3 (Bakhariya to Baron 2.5km) | Ashoka Buildcon | 8,75,00,000.00 | Auraiya (UP) | Roads |
| 6 | Udaipur Ring Road Earth Work & Structure | Ravi Infrabuild | 3,63,00,000.00 | Udaipur (Raj) | Roads |
| 7 | Bangalore–Chennai Expressway Ph 2 Pkg-2 (3 km) | Monte Carlo | 3,25,00,000.00 | Karnataka | Roads |
| 8 | Earth Work in Sanchore–Santalpur Pkg-2 (Amritsar–Jamnagar) | Ravi Infrabuild | 5,73,00,000.00 | Tharad (Guj) | Roads |
| 9 | Delhi–Vadodara Expressway Pkg-29 (5 km) | PNC | 7,50,00,000.00 | Panch (Guj) | Roads |
| Total Value Of Completed Work | 73,31,00,000.00 | ||||
Ganga Expressway
Description of the Project:
Ganga Expressway is an under-construction, 594 km (369 mi) long, 6-Lane (expandable
to 8) wide greenfield expressway in the state of Uttar Pradesh
Vishal projects got 1 km earth work in 6 Lane road work from our client ITD
Cementation Pvt.Ltd in Pkg-11 Earth work in 1 km is approximately 4,16,000 Cum
The works consists of the following:
1. Earthworks (Including- Mining/Soil/Diesel/Local Problems/Permissions/
Excavation/Transportation/Grading/ Compacting /Watering)
Vishal Projects has done 4,16,000 Cum Work out of 1,08,000 In 2 Months.
Ganga Expressway
Description of the Project:
Ganga Expressway is an under-construction, 594 km (369 mi) long, 6-Lane (expandable
to 8) wide greenfield expressway in the state of Uttar Pradesh
Vishal projects got 1 km earth work in 6 Lane road work from our client ITD
Cementation Pvt.Ltd in Pkg-11 Earth work in 1 km is approximately 4,16,000 Cum
The works consists of the following:
1. Earthworks (Including- Mining/Soil/Diesel/Local Problems/Permissions/
Excavation/Transportation/Grading/ Compacting /Watering)
Vishal Projects has done 4,16,000 Cum Work out of 1,08,000 In 2 Months.
Growth Chart
Since the establishment of vishal projects firm for road works since 2011, the firm has registered constant growth in respect of number of projects executed, as shown in the figure above, growing projects values varied nature of projects like roads, bridges, canal works, dam works, drainage works, etc.; increased and wide exposure to all aspects of technical and operational factors and complexities, all of which have empowered the firm further to undertake and successfully complete a number of projects involving large contract values.